Domestic rates
What a home on the Domestic (LT) tariff (DLT) pays per unit after any subsidy built into the tariff.
| Units per month | Rate you pay |
|---|---|
| 1–100 | ₹5.00 |
| 101–200 | ₹5.04 |
| Above 200 | ₹5.10 |
Fixed charge: ₹90 per kVA of load per month
Example bills
| Units per month | Bill | Average per unit |
|---|---|---|
| 50 | ₹430.00 | ₹8.60 |
| 100 | ₹680.00 | ₹6.80 |
| 150 | ₹932.00 | ₹6.21 |
| 200 | ₹1,184.00 | ₹5.92 |
| 300 | ₹1,694.00 | ₹5.65 |
| 500 | ₹2,714.00 | ₹5.43 |
Sanctioned load 2 kW, urban, single phase. Duty and fuel surcharge excluded.
Where these rates come from
- Regulator
- MSERC
- Order
- MSERC Revised ARR & Distribution Tariff Order FY 2026-27 for MePDCL
- Dated
- 26 March 2026
- Distributors
- MePDCL
- Billing
- Monthly
- Document
- Open the tariff order (PDF)
Not in this estimate
- Fixed charge is per kVA; kW is used as kVA here.
- FPPCA and duty not included.
All LT tariff categories in Meghalaya
Every low-tension category in the order: homes, shops, industry, agriculture and more. Approved rates, before any government subsidy unless the order says otherwise.
KJ-MKutir Jyoti / BPL metered (up to 30 units/month)Verified
| Units | Rate |
|---|---|
| 1–30 | ₹4.57 /kWh |
Kutir Jyoti unmetered
Rs 210 per connection per month
Fixed charge: None
Units above 30 billed at domestic slab rates.
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.1(i) p.103. Open the order
DLTDomestic (LT)Verified
Homes; places of worship; non-profit hospitals, schools and hostels; ashrams, dharamshalas, community halls; MeECL offices and staff residences
| Units | Rate |
|---|---|
| 1–100 | ₹5.00 /kWh |
| 101–200 | ₹5.04 /kWh |
| Above 200 | ₹5.10 /kWh |
Slabs are telescopic: each band of units is charged at its own rate.
Fixed charge: ₹90 per kVA of load per month
Unchanged from FY 2025-26.
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.1(ii) p.104. Open the order
CLTNon-domestic / commercial (LT)Verified
| Units | Rate |
|---|---|
| All units | ₹7.45 /kWh |
Fixed charge: ₹170 per kVA per month
Energy cut from 7.50.
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.2 p.104-105. Open the order
ILTIndustrial (LT)Verified
| Units | Rate |
|---|---|
| All units | ₹6.60 /kWh |
Fixed charge: ₹170 per kVA per month
Energy cut from 6.80.
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.3 p.105. Open the order
PL-MPublic lighting (metered)Verified
| Units | Rate |
|---|---|
| All units | ₹7.00 /kWh |
Fixed charge: ₹180 per kVA per month
Energy up from 6.35; unmetered lighting to be phased out.
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.4 p.106. Open the order
WSLTPublic water supply / sewage treatment (LT)Verified
| Units | Rate |
|---|---|
| All units | ₹7.00 /kWh |
Fixed charge: ₹180 per kVA per month
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.5 p.106-107. Open the order
GPGeneral purpose (Govt connections not in other categories)Verified
| Units | Rate |
|---|---|
| All units | ₹7.35 /kWh |
Fixed charge: ₹180 per kW per month
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.6 p.107. Open the order
APAgricultureVerified
| Units | Rate |
|---|---|
| All units | ₹3.15 /kWh |
Fixed charge: ₹130 per kW/HP per month
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.7 p.107-108. Open the order
CRMCrematoriumVerified
| Units | Rate |
|---|---|
| All units | ₹4.57 /kWh |
Fixed charge: ₹55 per kVA per month
Fixed charge changed from Rs 7,510/connection to Rs 55/kVA.
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.8 p.108. Open the order
EVCSEV charging stationsVerified
| Units | Rate |
|---|---|
| All units | ₹6.00 /kWh |
Fixed charge: None
The order's table header labels this row 'Crematorium (CRM)' by mistake.
Source: MSERC Order on Revised ARR & Distribution Tariff for FY 2026-27 for MePDCL (Case No. 11 of 2025, 26-03-2026), Ch.9 Schedule of Approved Tariffs for FY 2026-27, 9.1.9 p.108-109. Open the order
Meghalaya bill questions
How much is the electricity bill for 100 units in Meghalaya?
About ₹680.00 for 100 units in a month, using the current MSERC tariff. Sanctioned load 2 kW, urban, single phase. Electricity duty and the monthly fuel surcharge are not included.
What will 200 or 300 units cost in Meghalaya?
Roughly ₹1,184.00 for 200 units, and ₹1,694.00 for 300 units. Use the calculator above for your exact units and load.
Are Meghalaya domestic slabs telescopic?
Yes. Each band of units is charged at its own rate, so only the units above a slab boundary pay the higher rate.
How often are Meghalaya electricity bills issued?
Homes are billed monthly. Enter the units for one billing period.
Which tariff order are these Meghalaya rates from?
MSERC Revised ARR & Distribution Tariff Order FY 2026-27 for MePDCL, dated 26 March 2026. A link to the PDF is in the sources box on this page.
What does this estimate leave out?
Fixed charge is per kVA; kW is used as kVA here. FPPCA and duty not included.